Philéas MauryProject EngineerEnvelope lead, new build and refurbishment

Saint-Cyr-l’École · Yvelines (78)

240 occupied homes refurbished, 20 reconfigured and 40 new homes built

Fontaine Saint-Martin, secteur Est

  • Completed

January 2023–June 2026

My role

Project Engineer

In charge of the building envelope, new-build and refurbishment alike, and of financial and budget control.

Responsibilities

  • Building envelope for the new-build and refurbishment parts
  • Financial and budget control of the project

Site management team

  • Project manager
  • Envelope lead (my position)
  • Envelope works manager
  • Homes lead, new build and refurbishment
  • Homes works manager, new build and refurbishment
  • Site foreman

Scope of works

On the doorstep of Versailles, the Fontaine Saint-Martin district is getting a new lease of life. Its eastern sector is nine slab blocks from 1965, ground plus four storeys, with 260 homes, which Les Résidences Yvelines Essonne wanted to transform without emptying the buildings: throughout three and a half years of works, residents stayed in their homes, except those of the twenty restructured flats, who were rehoused.

The buildings have changed face. A coat of insulation finished in render and brick slips, new windows, perforated sheet-metal balustrades that filter the light, and stairwells turned into tall walls of glass blocks. The entrance lobbies were rebuilt or enlarged; inside the homes, ventilation, plumbing, electrics and finishes were renewed, and twenty of them were completely reconfigured.

Then, at the end of the blocks, the “Folies” were born: four new buildings set against the gable walls, providing 40 new homes. A 1960s district now aiming for energy rating C.

Show

The project in figures

  • 300homes delivered240 refurbished, 20 restructured, 40 new
  • 13buildings9 slab blocks from 1965 and 4 new Folies
  • 26stairwellslived in throughout the works
  • 3.5 yearsof works
  • 17,000 m²of façades renovated
  • 612window surrounds
  • 76people on site at the peaksite management included
  • 700 m²of glass blocks

Site plan

Nine occupied blocks, four Folies at their gable ends

The eastern sector of Fontaine Saint-Martin gathers nine 1965 slab blocks and four new buildings, the Folies, set against their gable walls.

123456789A'''BCDN50 m
Refurbished blocksNew Folies

Refurbishment · the works at a glance

Nine blocks redone, with residents at home

Façades, roofs, stairwells, halls and homes are redone without ever emptying the buildings.

  • 17,000 m²of façades renovated
  • 612aluminium window surrounds
  • 1,500 m²of perforated-sheet railings
  • 4,100 m²of roofs redone
  • 1,100 mof parapets raised
  • 240homes renovated
  • 26halls enlarged in steel and glass
  • 72metal doors to basements and shared stores
  • Plus de 9 000 m²of paint in the common areas
  • 390bike spaces

Refurbishment · 1 · FaçadesMy scope

The façade works

Once the stairwells are sawn out and the parapets raised, the 1965 façades get 14 cm of insulation, parapets included, then, over most of them, glued brick slips, from grey-black at the foot to light greige at the top.

One block, layer by layer
Front façadeRear façade
  1. Saw out the stairwells

    Before anything else, the stairwell façades are sawn out, then closed with glass blocks.

  2. Raise the parapets

    Masonry built on the existing upstand, to give a 1.10 m guarding height.

  3. Replace the windows

    New PVC windows, fitted with residents at home.

  4. Fit the window surrounds

    Gold Perla aluminium boxes around the windows, fixed to the concrete before the insulation.

  5. Insulate

    14 cm of graphite polystyrene, bonded and anchored, 18 cm at the foot of the façade; the insulation covers the parapets too.

  6. Slips and render

    Brick slips glued one by one up to the coping, three colours blended in six bands, render elsewhere.

  7. Gables

    Ventilated metal cladding in Gold Perla, on a frame.

  8. Shutters and railings

    Sliding shutters hung on the boxes at the front, perforated-sheet railings on the balconies at the rear.

After : A rear façade, before and after the works
Before : A rear façade, before and after the works
A rear façade, before and after the works
  • A special approval from the CSTB to glue brick slips up to 28 m high, instead of 12 m
  • 3brick colours blended in six bands, approved on a mock-up façade
  • 30pull-out tests to set the anchors
  • 600 m²of metal cladding on the gables
Brick slips and window surrounds

Refurbishment · stairwellsMy scope

26 stairwell façades cut out, then glazed

Each stairwell façade was sawn out over its full height, under containment, then replaced by a glass-block wall.

One stairwell, in five steps
ContainmentWinch11.8 m
  1. Contain

    A sheeted scaffold tower; residents come in through the basement of the next stairwell.

  2. Saw

    A diamond wall saw on a rail, cooled with water.

  3. Lower the blocks

    The cut panels go down on a winch.

  4. Rebuild the reveals

    Steel treated, reveals and head rebuilt.

  5. Set the glass blocks

    Precast panels lifted and fixed from a cherry picker.

  • 26stairwells
  • 700 m²of blocks
  • 11.8 mhigh
Before: the 1965 concrete stairwells
During: the contained sawing towers
After: the glass-block wall

Refurbishment · façadesMy scope

Parapets raised above the residents

To reach a 1.10 m guarding height, 1,100 metres of parapets are raised, with masonry built on top of the small existing upstand, then insulated like the façade.

The method, in four steps
Flat roofFaçadeOld railingExisting upstand, keptBars anchored every 20 cm≥ 1.10 m
  1. Prepare

    The old railings come off; the small existing upstand is kept.

  2. Anchor

    Bars chemically anchored every 20 cm into the existing upstand.

  3. Build up

    Reinforced formwork blocks, set on the existing upstand and checked as they go up.

  4. Pour, insulate and finish

    Concrete poured, insulation carried on from the façade, render and coping.

Refurbishment · façadesMy scope

Window surrounds that carry the shutters

Before the insulation, the windows get Gold Perla aluminium boxes, fixed to the concrete; in front of the bedrooms they also carry the sliding shutters’ rails.

One window surround, in section
InsideOutside20 cm
  1. The window

    The new PVC window goes into the old opening.

  2. The brackets

    Steel brackets anchored into the concrete, before the insulation.

  3. The box

    Head, reveals and sloping sill with a drip, riveted and sealed to the window.

  4. The insulation

    14 cm of insulation then laid around the box, a thin return in the reveal, a fire strip above.

  5. Brick and shutter

    The brick slips run up to the box, and the sliding shutter hangs from its rail.

  • 612boxes made to measure
  • Plus de 13 mfor the longest, running along a whole row of windows
  • 1,500 m²of perforated-sheet railings
  • 1,200 m²of sliding aluminium shutters
  • 250 m²of canopies over the top-floor balconies
Window surrounds and glass blocks
Perforated-sheet railings

Refurbishment · 2 · Homes

240 homes, 240 projects

Each home had its own survey and options, and each tenant their own dates, for made-to-measure works.

A through home, trade by trade
BalconyKitchenBathBedroomHallWCLiving roomBedroomLandingNew fittingsSink and worktopNew riserConsumer unitExtract ventsWater heaterNew windows1Plumbing2Gas and electrics3Ventilation4Hot water5Windows
  1. Plumbing

    Stacks replaced one by one, then bath, vanity unit, toilet or sink as each home needs.

  2. Gas and electrics

    Gas is removed or brought up to standard in the kitchens, and the wiring is redone or made safe depending on the home.

  3. Ventilation

    Ventilation redone and rubbish chutes sealed in every home.

  4. Hot water

    Water heaters replaced where needed, often moved into the bathroom.

  5. Windows

    New PVC windows, fitted with residents at home.

Refurbishment · 3 · Common areasMy scope

26 halls enlarged in steel and glass

The old entrances are partly demolished and the halls enlarged with a glazed lobby on a steel frame, with a side door sheltered under the canopy.

One hall, in five steps
Old entranceEntranceLetterboxesStairs5.34 m
  1. Demolish the old entrance
  2. Pour the slab
  3. Put up the steel frame
  4. Roof it, with a canopy
  5. Glaze and fit it out
  • 26halls enlarged with a lobby
  • 26letterbox banks
  • 130fire-rated units, laminated glass
  • 3,200 m²of sprayed insulation in the basements
An entrance before the works
A finished hall

Refurbishment · performance

From energy label D to C

Insulation, windows and roofs move the nine blocks up one energy class.

Energy label
  • 46 %less energy used
  • 64 %less heat loss
  • 17,000 m²of façades renovated
  • 4,100 m²of roofs redone
  • 3,200 m²of basement ceilings insulated

New build · the works at a glance

Four Folies, from piles to roof

Four new buildings built against occupied blocks, on ground that called for deep foundations.

  • 115bored piles, and 29 micropiles
  • Plus de 900 m³of concrete in walls and beams
  • 3,800 m²of floor slabs
  • 28balconies
  • 211aluminium windows
  • 322doors
  • 4lifts
  • Plus de 2 300 m²of new façades

New buildMy scope

The Folies, built against occupied buildings

Four six-storey buildings on piles, joined to the gable walls of the blocks by an expansion joint.

A Folie against the gable of a block
1965 block, occupiedB1GFR+1R+2R+3R+4R+5New FolieExpansion joint
  • 20homes served by Folie A’’’ (10 new, 10 restructured), between buildings 2 and 3
  • 15homes served by Folie B (5 new, 10 restructured), between buildings 5 and 6
  • 14homes in Folie C, with a shop
  • 11homes in Folie D, with a coworking space
A Folie under construction
A finished Folie, against the gable of a block

New build · façadesMy scope

Façades of Gold Perla metal blades

Above a ground floor in grey brick slips, the Folies are insulated from the outside then clad in tall vertical blades of coated metal in Gold Perla, the colour of the window surrounds of the blocks.

A Folie, layer by layer
  1. Windows

    Coated aluminium windows and French windows, with roller shutters.

  2. Insulate

    14 cm of insulation on the concrete walls.

  3. Frame

    A metal frame, leaving an air gap behind the cladding.

  4. Cladding

    Gold Perla vertical blades, laid in bands of two storeys separated by a flashing, and corrugated sheet at the back of the loggias.

  5. Brick

    Grey brick slips glued on the ground floor.

  6. Railings

    Barred steel railings, fixed to the slab edge.

  • Plus de 2 300 m²of new façades
  • 1,400 m²of Gold Perla vertical blades
  • 211aluminium windows and doors
  • 28balconies
Gold Perla blades, windows and railings
The balconies of a Folie

Heavy restructuringMy scope

20 homes stripped of asbestos, then rebuilt

The end-of-block homes next to Folies A and B were fully stripped of asbestos, then restructured to open onto the new landings and lifts.

  • 20homes restructured, from the ground to the fourth floor
  • Asbestos removed under containment, through a separate access tower so residents kept their stairs
  • 17 tof waste removed and tracked
  • Independent final checks passed, then new partitions, openings and services
A stripped-out home, before its restructuring

Project team

Client and design team

  • Les Résidences Yvelines EssonneClient (housing provider)
  • SCP Béguin & MacchiniArchitect (lead designer)
  • BETEM Île-de-FranceLead engineering consultant
  • ArgeniumAsbestos removal
  • SETURoads and utilities
  • GambaAcoustics

Inspection, safety and scheduling

  • Alpha ContrôleTechnical inspection body
  • BTP ConsultantsHealth and safety coordinator
  • SCEScheduling and site coordination

Construction

  • IRIS / Groupe Léon GrosseGeneral contractor
Project rendering
Project rendering
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works

1 / 7

Philéas MauryProject ManagerRunning the project

Marly-le-Roi · Yvelines (78)

Refurbishment of 262 occupied homes

Fonds de Montval & Haut et Bas Picard

  • In progress
  • Refurbishment of occupied housing

January 2026–2028

My role

Project Manager

Site preparation, technical management of the work packages and budget control, working closely with the client and the residents.

Responsibilities

  • Site preparation: tendering and approval of subcontractors, detailed programme, site set-up
  • Technical management of the envelope, homes and common areas work packages
  • Budget control, quotes for additional works, subcontract amendments
  • Issue and tracking of construction documents (document management, approvals)
  • Liaison with the client, the architect and the engineering consultants
  • Organisation of works in occupied housing with the resident liaison officer

Site management team

  • Construction director
  • Project manager (my position)
  • Homes lead
  • Façades works manager

Scope of works

In Marly-le-Roi, Léon Grosse is refurbishing 262 social homes in nine buildings from 1978, for Les Résidences Yvelines Essonne. It is a global performance contract: the same team designs the works, builds them and commits to the energy results.

The façades get insulated cladding, in rendered boards or natural stone, the windows are replaced and the open walkways closed in. Inside the homes, radiators, water heaters, ventilation and entrance doors are replaced, with residents at home.

The project in figures

  • 262homeslived in throughout the works
  • 9buildings from 1978on two estates
  • 17,000 m²of façades re-clad
  • 56walkways closed in
  • 1,671new windows
  • 1,310connected radiators
  • 260new entrance doors
  • 2028planned handover

Site plan

Two estates, nine hexagon buildings

Seven « serpent » buildings with open walkways and two star-shaped ones, all five storeys high, on sloping ground.

246101137N50 m
Haut et Bas Picard
212325N20 m
Fonds de Montval

The works at a glance

Nine buildings renovated, from façades to homes

Façades, walkways, homes and common areas are all redone in one project, with residents at home.

  • 1,671new windows, 428 of them fire-resistant
  • 17,000 m²of façades re-clad and insulated
  • 4,000 m²of natural stone cladding
  • 260acoustic, flame-retardant entrance doors
  • 1,200 m²of balcony waterproofing
  • 1,310connected radiators
  • 262new water heaters
  • 262homes with humidity-controlled ventilation
  • 212emergency lights
  • 11,000 m²of paint in the common areas

1 · FaçadesMy scope

Real cladding, not just render

Over 14 cm of rock wool, a metal frame carries rendered cement boards or natural stone, with a ventilated air gap behind.

A « serpent » building, layer by layer
  1. Replace the windows

    Double-glazed PVC windows, fitted before the cladding.

  2. Insulate

    14 cm of rock wool on the 1978 concrete.

  3. Fix the frame

    Steel brackets and rails, leaving a ventilated air gap.

  4. Boards and render

    Cement boards screwed to the rails, then a smooth or scraped render.

  5. Natural stone

    2 cm limestone slabs, hung on aluminium rails.

  6. Base

    Fibre-cement panels at the foot of the façade, tougher against knocks.

Close-up: the rendered façade
HomeOutside1978 concreteRock woolAir gap and steel frameCement boardReinforced render
Close-up: the stone façade
HomeOutside1978 concreteRock woolAir gap, tubes and railsGrooved stone,hung on the rails

2 · Homes

Five visits per home

By appointment, five jobs follow one another in each home, with residents at home.

A home, visit by visit
KitchenLiving roomBedroomHallBathroomWCStoreBedroomLandingConsumer unitExtract ventsRadiatorsWater heaterNew windowsEntrance door1Radiators and electrics2Water heater3Ventilation4Windows5Entrance door
  1. Radiators and electrics

    Connected electric radiators replace the old electric heating, and the wiring is made safe.

  2. Water heater

    A new electric water heater, fitted within the day.

  3. Ventilation

    Humidity-controlled vents and air inlets, doors trimmed so the air can flow.

  4. Windows

    Double-glazed PVC windows and new roller shutters.

  5. Entrance door

    Acoustic, flame-retardant door with a three-point lock.

3 · Walkways and common areasMy scope

56 walkways closed in

The open-air walkways are closed in, which ends the damp and turns them into fire-protected corridors.

One walkway, in section
HomeWalkwayOutside1.15 mSlatsSteel frameon the sillFixingsinto the concreteCladding
  1. Before

    1.15 m wide, a concrete parapet, slats running in front of the façade, and condensation on the walls.

  2. Take down the slats

    The slats and the steel frame that carries them, resting on the concrete sill, are taken down from the outside.

  3. Prepare

    A reinforced-concrete tie beam is cast on the kept parapet.

  4. Close in

    Aerated-concrete blocks go up to the slab, or a window is set on the parapet.

  5. Clad

    The same cladding as the rest of the façade, on a frame fixed into the concrete, above and below the blocks.

  6. Fit out

    Acoustic ceiling, fire-resistant windows on the homes’ side, a flame-retardant door to the stairs.

  • 7« serpent » buildings with walkways
  • 310fire-resistant windows on the homes’ side
  • 111common-area doors, 87 of them fire-resistant
  • About fifteen homes enlarged by some 2 m² at the end of a walkway
  • A smoke vent at the top of each stair, acoustic ceilings in the halls and corridors
A walkway and its slats, before the works
The parapet that is kept

Performance

A commitment on energy use

Designed and built by the same team, the project commits to bringing the buildings to energy label C.

Energy label
  • Jusqu’à 48 %less energy used, depending on the building
  • 17,000 m²of façades insulated
  • 1,671new windows
  • 56walkways closed in
  • 262homes with humidity-controlled ventilation

What makes this project complex

  • Designing and building at once, with a commitment on energy use.
  • 262 occupied homes on two estates.
  • Closing in 56 walkways above the residents.
  • Sloping ground and raised entrance halls.

Key milestones

  1. July 2025Detailed design
  2. January 2026Preparation starts
  3. February 2026Public meeting
  4. Spring 2026Show flat
  5. May 2026Works start
  6. 2028Planned handover

Project team

Client and design team

  • Les Résidences Yvelines EssonneClient (housing provider)
  • Roubaud ArchitectesArchitect (lead designer)
  • COTECBuilding engineering, all trades
  • Pouget ConsultantsThermal and building services engineering

Inspection, safety and scheduling

  • Point ContrôlesTechnical inspection body
  • Bureau VeritasHealth and safety coordinator

Construction

  • IRIS / Groupe Léon GrosseGeneral contractor
Project rendering
Project rendering
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Before the works
Project rendering
Project rendering

1 / 11

Philéas MauryMulti-site Project ManagerRunning projects on several sites

Suresnes · Hauts-de-Seine (92)

Refurbishment of 114 occupied homes, Suresnes garden city

Cité-jardin de Suresnes

  • In progress
  • Refurbishment of occupied housing

November 2026–2028

My role

Multi-site Project Manager

Multi-site project manager, running Suresnes and Marly-le-Roi in parallel.

Site management team

  • Construction director
  • Multi-site project manager (my position)
  • Homes lead
  • Façades works manager

Scope of works

In the garden city of Suresnes, a listed site, Léon Grosse is refurbishing 114 social homes for Hauts-de-Seine Habitat, in three buildings from 1956.

The façades are insulated with rock wool, under render or behind brick cladding, in colours approved with the heritage architect; windows, entrance doors and halls are redone. Inside the homes, heating, ventilation, plumbing and electrics are upgraded, and hot water now comes from the boiler room, with residents at home.

The project in figures

  • 114homeslived in throughout the works
  • 3buildings from 1956in a protected garden city
  • 9halls and stairwells
  • 637new windows
  • 5,000 m²of insulation fitted
  • 48workers at the peak
  • 1home opened each day
  • 2028planned handover

Site plan

Three buildings around a garden

At the heart of the estate, on a listed site, the central garden stays open to residents during the works.

ABCN20 m
Refurbished buildings
  • 64homes in building A, rue Kellogg, 8 storeys
  • 30homes in building B, 5 storeys
  • 20homes in building C, 5 storeys
  • Colours and materials chosen with the heritage architect

The works at a glance

The whole building, from roof to basement

Envelope, homes, common areas and boiler room are all redone in one project, with residents at home.

  • 637new PVC windows, 557 with roller shutters
  • 5,000 m²of 14 cm rock wool
  • 1,500 m²of brick cladding
  • 114fire-rated entrance doors
  • 1,400 m²of roofs cleaned and treated
  • 436low-temperature radiators
  • 342new extract vents
  • 700 mof new hot-water risers
  • 114homes rewired
  • Rue Kellogg car park resurfaced at the end of the works

1 · Façades

Insulating without betraying the garden city

The old insulation is stripped, then the façades are redone in light render, and in brick cladding on the ground floor, the stairwells and the rear façade of building A.

Building A, layer by layer
  1. Insulate

    14 cm of rock wool on the 1956 concrete, bonded and anchored under the render, anchored behind the brick.

  2. Fix the frame

    Under the brick, a metal frame leaves a ventilated air gap, closed off at every floor.

  3. Clad

    Brick-slip panels screwed to the frame, light render everywhere else.

  4. Replace the windows

    Double-glazed PVC windows with built-in roller shutters.

  5. Make safe

    Aluminium railings on the French windows.

Close-up: the brick cladding
HomeOutside1956 concreteRock woolVentilated air gapand metal frameBrick-slip panels,screwed on
Close-up: the rendered façade
HomeOutside1956 concreteRock wool, bondedand anchoredReinforced render,floated finish
The garden city before the works

2 · Homes

One home opened each day

Each home is brought up to date, from windows to hot water, while its residents live there.

A home, trade by trade
KitchenLiving roomBedroomHallBathroomWCStoreBedroomLandingNew fittingsSink and worktopNew riserConsumer unitExtract ventsRadiatorsNew windowsEntrance door1Windows and door2Bathroom and kitchen3Electrics4Ventilation5Heating6Hot water7Wet rooms
  1. Windows and door

    Double-glazed PVC windows and a fire-rated entrance door, fitted over the old frames.

  2. Bathroom and kitchen

    New bath or shower, basin, toilet and sink, with their connections.

  3. Electrics

    Wiring redone to standard, from the consumer unit to the sockets, with a smoke detector.

  4. Ventilation

    Air comes in through the bedroom and living-room windows, and leaves through the kitchen and bathroom.

  5. Heating

    Low-temperature radiators with connected thermostatic heads, and a towel rail.

  6. Hot water

    The electric water heater goes; hot water comes from the boiler room through a new riser that runs through the bathroom.

  7. Wet rooms

    New floor and paint in the kitchen, bathroom and toilet, tiles around the sink, the basin and the bath or shower.

3 · Common areas

Redesigned halls, and hot water under the garden

The nine halls are redone, and a new hot-water plant runs from the boiler room to the two other buildings under the garden.

Halls and stairwells

  • 9halls with glazed doors and access control
  • 64built-in letterboxes
  • 275LED lights with presence detection
  • Plus de 600 m²of terrazzo restored in the stairwells
  • 57rubbish-chute hatches sealed

Shared hot water

  • A condensing boiler added in the boiler room, with a 1,500-litre tank
  • 2buried links under the garden
  • 18new risers through the bathrooms
  • 132floor corings

Performance

From energy label D to C

Insulation, windows, ventilation and low-temperature heating more than halve the buildings’ energy use.

Energy label
  • 55 %less energy used
  • 5,000 m²of insulation fitted
  • 637new windows
  • 436low-temperature radiators
  • 342new extract vents

What makes this project complex

  • A protected heritage site, under the eye of the heritage architect.
  • Shared hot water created in occupied homes.
  • Buried pipes under a garden that stays open.
  • A primary and a secondary school right opposite.

Key milestones

  1. June 2025Agreement with the tenants and public meeting
  2. November 2026Preparation starts
  3. 2027Works start
  4. 2028Planned handover

Project team

Client and design team

  • Hauts-de-Seine HabitatClient (housing provider)
  • Groupe AIPArchitect (lead designer)
  • Thermi-ClimThermal and building services engineering

Inspection, safety and scheduling

  • BTP ConsultantsTechnical inspection body
  • BECSHealth and safety coordinator

Construction

  • IRIS / Groupe Léon GrosseGeneral contractor